Painting to the pool walls and base is complete.
The paint needs 5-7 days to cure, during this curing time, the remainder of the final tile work will take place and we expect to begin to fill the pool on Friday November 5th or Monday November 8th. In order to expediate the water filling and treatment time, we will filling the pool using water trucks. This water from the trucks will be cleaner, therefore will require a shorter treatment time, and will also reduce our filling time by up to 3 days!

Balancing of the water will occur the week of November 8th and inspections conducted, with the goal to have the pool re-open no later than November 15th.
Please stay tuned for any changes.